"On June 27, Castorone, one of the vessels responsible for the construction of Baltic Pipe between Poland and Denmark, began laying the gas pipeline on the Baltic seabed," Gaz-System, the pipeline's operator, wrote in a communique on Monday.
The Baltic Pipe will bring Norwegian gas to Poland, and the goal is to finish the project by 2022. Gaz-System CEO stated that his company planned to lay 275 kilometres of the pipeline on the Baltic seabed by the end of the year.